Cameo - This week marks the beginning of the end for a piece of Western Slope history. Xcel's power plant in Cameo is getting ready to come down.

The dismantling of the 1,100 acre plant, which stopped its operations in December 2010, is expected to begin by the end of the year. A $5 million decommissioning contract for the plant was just awarded to the Gilmore Team, which will subcontract the work to multiple firms. However, because of environmental concerns due to the age of the 50-year-old plant, precautions are being taken first.

"The first thing they'll do is go after the asbestos, and we need to have the asbestos abated and made safe before we do any of the actual demolition work. So there'll be several months here where it doesn't look like much is happening, but we're rendering the place safe for people to go work in," explained Fred Eggleston, an area manager for Xcel Energy.

Meetings start this week, but it could still be another couple years before the plant is completely dismantled. There's no word yet on a future plan for the site.

Add a comment

Name:

Comment: 1000 Characters Left

KREX - News, Weather, Sports for Grand Junction | Montrose | Glenwood Springs - Coverage You Can Count On and its affiliated companies are not responsible for the content of comments posted or for anything arising out of use of the above comments or other interaction among the users. We reserve the right to screen, refuse to post, remove or edit user-generated content at any time and for any or no reason in our absolute and sole discretion without prior notice, although we have no duty to do so or to monitor any Public Forum.

Most Popular

This content requires the latest Adobe Flash Player and a browser with JavaScript enabled. Click here for a free download of the latest Adobe Flash Player.
News Channel 5 Weather